ENGINEERING DIVISION MEMORANDUM
June 24, 2019 TO: City Council FROM: Mike Payne, City Engineer SUBJECT: Consideration and action to award contracts for Bid Schedule “D” - 2019: C2019-12 Landfill Phase 6 Construction
C2019-13 Lower Court House Park Lighting Improvements
Relates to Strategic Plan Strategic Goal - Infrastructure
These contracts support the City’s efforts to maintain existing infrastructure and continue to provide municipal services. Executive Summary Bids for C2019-11, Northeast Regional Trail, C2019-12, Landfill Phase 6 Construciton and C2019-13, Lower Court House Park Lighting Improvements, were opened May 15, 2019. A DOT grant is funding the majority of C2019-11. DOT is reviewing the bid information for the Northeast Regional Trail project. Staff anticipates bringing that contract back to Council at the July 22 meeting for consideration of award after DOT accepts the bid. One incomplete bid was received for C2019-13 so that bid was not opened and Council will be asked to reject that bid. City Recommendation The City recommends awarding contract C2019-12, Landfill Phase 6 Construction to the low
bidder and rejecting contract C2019-13, Lower Court House Park Lighting Improvements due to receiving one incomplete bid. Funding for C2019-12, Landfill Phase 6 Construction will be over two years so Council should expresses an intent to borrow the remaining funding in 2020. Suggested Motion
I move to award contract C2019-12, Landfill Phase 6 Construction to the low bidder as described in the memo and to express an intent to borrow funds as outlined in the memo. The motion should also include rejecting the incomplete bid for contract C2019-13, Lower Court House Park Lighting Improvements. Background
C2019-12 – Landfill Phase 6 Construction – For furnishing all the labor, materials, equipment, and doing all the work necessary for construction of a landfill liner to include: subbase excavation and filling ; gradient control piping and trench; 4-foot thick compacted clay liner; 60-mil geomembrane liner with geotextile cushion; leachate drainage layer and sump; leachate collection piping, pump, manholes, fittings, sampling station, meters, and controls; access road
2
improvements; storm water drainage; fencing; site restoration; monitoring well abandonment and gas probe installation; and incidentals shown on the plans and specified herein for Landfill
Phase 6 Construction. There were seven (7) qualified plan holders. The contract estimate was $4,986,536.10. Staff received three (3) bids with Meise Construction, Inc. providing the lowest bid. The Engineering Division is recommending award of this contract to Meise Construction, Inc. of Sauk City, WI for a total bid amount of $5,068,485.30. Meise Construction Inc Post Office Box 118
Sauk City, WI 53583
Total: $5,068,485.30
Frank Silha & Sons Excavating, Inc 348 HWY 14 East Janesville, WI 53546
Total: $5,466,755.05
RiverView Construction Inc. 4140 N 6th St
Wausau, WI 54403
Total: $5,829,154.75
Anticipated Project Costs:
Contract Base Bid $5,068,485.30
Contingency (7.5%) 380,000.00
Consulting 362,000.00
Engineering 9,514.70
Total $5,820,000.00
Project Funding:
2019 Note – Sanitation Fund 2,000,000.00
2019 Operating – Sanitation Fund 500,000.00
2020 Note – Sanitation Fund 3,320,000.00
Total $5,820,000.00
C2019-13 – Lower Court House Park Lighting Improvements – For furnishing all the labor, materials, equipment, and doing all the work necessary for the construction and completion of approximately 1,700’ of electrical conduit; 5,100’ of electrical wire; 14 light bollards; 9 light posts and fixtures and other landscape lighting; 3 pull boxes; 600 square feet of concrete flatwork; removal and salvage of existing light posts and fixtures; restoration; and incidental construction. There was one (1) qualified plan holder. The contract estimate was $144,288.00. Staff received one (1) bid from Van Brocklin Electric which was rejected due to an incomplete bid submittal due to not including the signature page or the affidavit of organization.
Options
• Approve City recommendation to award contract C2019-12.
• Refer back to staff with guidance on how the council wishes to proceed.
• Do not award the contract as recommended by staff.
3
Analysis Included in the ‘Background’ section.
Conclusions
These contracts support tasks listed in the 2019-2023 Strategic Plan. Restated City Recommendation
The City recommends awarding contract C2019-12, Landfill Phase 6 Construction to the low bidder and rejecting contract C2019-13, Lower Court House Park Lighting Improvements due to receiving one incomplete bid. Funding for C2019-12, Landfill Phase 6 Construction will be over two years so Council should expresses an intent to borrow the remaining funding in 2020. cc: Mark Freitag, City Manager
Maggie Darr, Assistant to the City Manager Paul Woodard, Director of Public Works