ENGINEERING DIVISION MEMORANDUM
November 9, 2020 TO: City Council FROM: Brad Reents, Assistant City Engineer SUBJECT: Consideration and action to award contract for Bid Schedule “E” - 2020: C2020-14 Sanitary and Storm Sewer Lining C2020-15 City Hall Improvements
C2020-16 Senior Center HVAC Improvements
Relates to Strategic Plan Strategic Goal - Infrastructure
These contracts support the City’s efforts to maintain existing infrastructure and continue to provide municipal services. Executive Summary Bids for C2020-14 Sanitary and Storm Sewer Lining, C2020-15 City Hall Improvements and C2020-16 Senior Center HVAC Improvements were opened October 21, 2020. City Recommendation
The City recommends awarding contracts C2020-14 Sanitary and Storm Sewer Lining, C2020-15 City Hall Improvements and C2020-16 Senior Center HVAC Improvements as well as expressing the intent to borrow funds as outlined in the memo. Suggested Motion I move to award contracts C2020-14 Sanitary and Storm Sewer Lining, C2020-15 City Hall
Improvements and C2020-16 Senior Center HVAC Improvements as outlined in the memo. Background
C2020-14 Sanitary and Storm Sewer Lining – For furnishing all the labor, materials, equipment, and doing all the work necessary for the cured-in-place (CIP) trenchless lining rehabilitation and selective joint grouting of approximately 10,500 LF of 8”-33” diameter sanitary and storm sewer. There were six (6) qualified plan holders. The contract estimate was $773,612.00. Staff received three (3) bids with Visu-Sewer Inc. providing the lowest bid. The Engineering Division is recommending award of this contract to Visu-Sewer Inc. of Pewaukee, WI for a total bid amount of $609,693.00.
Visu-Sewer Inc. W230 N4855 Betker Dr Pewaukee, WI 53072
Total Bid: $609,693.00
2
Insituform Technologies 580 Goddard Ave
Chesterfield, MO 63005
Total Bid: $838,065.90
Granite Inliner, LLC PO Box 353 16028 Forest Blvd. N.
Hugo, MN 55038
Total Bid: $882,304.00
Anticipated Project Costs:
Contract 609,693.00 Contingency (10%) 60,307.00
Total $670,000.00
Project Funding:
2021 – WW Utility (lining) 250,000.00 2021 – WW Utility (infiltration reduction) 260,000.00 2020 and 2021 Operating Budget SW Utility (lining) 160,000.00
Total $670,000.00
C2020-15 City Hall Improvements – For furnishing all the labor, materials, equipment, and
completing all work necessary to replace the existing building fire alarm system and convert an existing lobby alcove to work space.
There were three (3) qualified plan holders. The contract estimate was $315,000.00. Staff received three (3) bids with Gilbank Construction Inc. providing the lowest bid. The Engineering Division is recommending award of the bid to Gilbank Construction Inc. of Clinton, WI for a total bid amount of $199,400.00. Gilbank Construction Inc.
301 Scot Dr Clinton, WI 53525
Total Base Bid: $199,400.00
Altmeyer Electric 827 S 21st St Sheboygan, WI 53081
Total Base Bid: $237,900.00
Westphal & Company
14 Marsh Court Madison, WI 53707
Total Base Bid: $295,459.00
3
Anticipated Project Costs: Contract 199,400.00
Engineering & Contingency (15%) 30,000.00 Design 65,000.00 Asbestos 15,000.00 Arc Flash Study 15,600.00 Force Account 10,000.00
Total $335,000.00 Project Funding: 2021 Note – General Fund 335,000.00
Total $335,000.00
C2020-16 Senior Center HVAC Improvements – For furnishing all the labor, materials, equipment, and completing all work necessary for a mechanical system replacement in the entire building, as well as a roof replacement and main entry replacement. The alternate bid item provides a cost for five (5) years of maintenance. A discussion with staff indicated Technical Services could likely complete the maintenance work more cost effectively so the City is not intending to award the alternate bid item.
There were two (2) qualified plan holders. The contract estimate was $600,000.00. Staff received two (2) bids with Gilbank Construction Inc. providing the lowest bid. The Engineering Division is recommending award of the base bid to Gilbank Construction Inc. of Clinton, WI in the amount of $471,250.00.
Gilbank Construction Inc. 301 Scot Dr Clinton, WI 53525
Total Base Bid: Alternate: Base Bid + Alternate:
$471,250.00 27,988.00 $499,238.00 Progressive Construction Services LLC 944 N Parker Dr Janesville, WI 53545
Total Base Bid: Alternate: Base Bid + Alternate:
$498,800.00 30,000.00 $528,800.00
Anticipated Project Costs: Contract (Base Bid) 471,250.00
Engineering & Contingency (15%) 68,750.00 Design 45,000.00 Asbestos 75,000.00
Cleaning Building Exterior 35,000.00
Total $695,000.00
Project Funding: Prior Note – General Fund 50,000.00 2021 Note – General Fund 645,000.00
Total $695,000.00 Options
• Approve City recommendation award contracts C2020-14, C2020-15 and C2020-16.
4
• Refer back to staff with guidance on how the Council wishes to proceed.
• Do not take action on the contracts as recommended by staff.
Analysis Included in the ‘Background’ section. Conclusions This contract supports tasks listed in the 2020-2024 Strategic Plan. Restated City Recommendation The City recommends awarding contracts C2020-14 Sanitary and Storm Sewer Lining, C2020-15 City Hall Improvements and C2020-16 Senior Center HVAC Improvements as well as expressing the intent to borrow funds as outlined in the memo.
cc: Mark Freitag, City Manager Maggie Darr, Assistant to the City Manager
Paul Woodard, Director of Public Works