Loading...
#2 Presentation of proposed 2011 sidewalk program PUBLIC WORKS DEPARTMENT MEMORANDUM September 22, 2010 TO: City Council FROM: Carl J. Weber P.E., Director of Public Works SUBJECT: Direction to Staff on Implementation of Installation of Planned Unfunded Sidewalks: Pedestrian Transportation Corridor Plan Staff Recommendation Staff recommends the City Council approve a ranking system for the multiyear planned unfunded sidewalk installation, replace the special assessment procedure used in the past with a billing process authorized by State Statute 66.907 and schedule a public hearing for October 25, 2010 to receive comment on the locations considered for inclusion in the 2011 program. City Manager’s Recommendation The City Manager concurs with the recommended approach. I believe this approach is consistent with previous Council discussions. Suggested Motion I move to approve the ranking system for the multiyear planned unfunded sidewalk installation as presented, to schedule a public hearing on October 25, 2010 for the purpose of receiving comments on the 2011 considered locations and to direct staff to notify the abutting property owners of the tentative 2011 sidewalk program prior to the public hearing. Request The City Council, at its July 12, 2010 regular meeting, directed staff to proceed with the installation of the planned unfunded sidewalks from the previously adopted Pedestrian Transportation Corridor Plan (PTCP). Because of the large quantity of walk to be installed, staff has prepared and is seeking approval of a plan to prioritize and schedule completion of the sidewalk over a number of years in an orderly and efficient manner. Background  City Council Direction The PTCP adopted by the City Council on January 14, 2008 includes 63 miles of planned unfunded sidewalks. The City Council directed staff to proceed with the installation of the planned unfunded sidewalk on July 12, 2010, completing 5 to 9 miles of construction each year until completed and commencing in 2011. 1  Ranking To provide for orderly scheduling of the directed work, staff developed a ranking system which considered: 1. Development status 2. Land use 3. Proximity to schools 4. Traffic volume 5. Presence on a bus route Item 1 above considered streets with current conditions unsuitable for the installation of sidewalk. This involved streets primarily along the periphery of the City with rural cross sections, open ditches, prohibitive cross slopes or other major obstructions. This initial screening resulted in the recommended deferral of 17 of the original 63 miles of planned unfunded sidewalks. The remaining 47 miles of sidewalks were ranked using the following point system: 1. Zoning a. 0 points - Agricultural, conservation and mining (A,C & M) b. 1 point – Low density residential (R1 & 2) c. 2 points - Industrial (M1 thru 4) d. 3 points - Business or Office (B1 thru 6, BT and O1 thru 3) e. 4 points – Medium to high density (R3, R3M & R4) 2. School Proximity a. 1 point - Between ¼ and ½ mile radius b. 2 points - Within ¼ mile of schools 3. Street Classification a. 0 points - Local b. 1 points - Collector c. 2 points – Minor Arterial d. 3 points – Principle Arterial 4. On bus route a. 0 points - No b. 1 point – Yes  Scheduling Approximately one half (25 miles) of the streets received a ranking of 3 to 7 (with 7 being the highest priority) and the remaining (21 miles) ranking 1 to 2. In order to achieve construction and management efficiencies while giving priority to higher ranked locations, a schedule was devised to group work in adjacent PTCP zones and to make an initial pass of the City completing the locations ranked 3 or higher and then a second pass for the locations ranked below 3. With this in mind the following schedule was developed: PTCP Zones Rank Miles Year 3 & 4 3 thru 7 5.68 2011 1 & 2 3 thru 7 5.19 2012 7 & 8 3 thru 7 7.58 2013 2 5,6 & 9 3 thru 7 6.89 2014 2,3 & 4 1 & 2 6.95 2015 1,6 & 7 1 & 2 7.56 2016 5,6 & 9 1 & 2 6.88 2017 Locations designated as deferred would be worked into the schedule as their status changes. Also, any gaps within a block where partial existing walk exists would be installed along with the locations ranked 3 thru 7 in the same PTCP zone.  Public Hearing To allow affected property owners time to comment on sidewalk orders and/or to fiscally plan for the cost of installation, a public hearing will be held before the council each fall preceding the scheduled construction year for those locations included in the following year’s program. Staff will prepare a recommended list of locations based on the approved schedule. The final list of locations to receive sidewalk installation orders will be approved by the City Council following the public hearing. The hearing for 2011 installations can be th scheduled for the October 25 meeting.  Billing st Property owners will be given until May 31 of the year following notification to complete private installation of ordered sidewalk. Any sidewalk not installed by the property owner will be installed through a bid contract by the City with the cost thereof billed to the property owner. Once invoiced, the property owner will be given three (3) payment options. ST 1. They can pay the invoice in full by October 31 2. They can have the invoice rolled over onto their property tax bill and incur no interest. 3. If the bill is over $250 they can elect to use the five-year payment plan and incur interest charges. To allow for an approximate 6 month notice of sidewalk installation orders, it is recommended that the City use the procedure authorized by State Statute 66.0907 rather than the special assessment process. This will allow staff to notify property owners of an estimate of the installation cost rather than the current process of bidding projects in advance of the special assessment process. This will also provide efficiencies in the invoicing process. cc: Eric Levitt, City Manager Jacob J. Winzenz, Assistant City Manager/Dir. of Administrative Services 3