Bid Tabs C2009-29, Landfill Gas Collection System CITY OF JANESVILLE BID DATE: DECEMBER 2, 2009 PUBLIC WORKS BID SCHEDULE "L" - 2009 CONTRACT 2009-29, LANDFILL GAS COLLECTION SYSTEM - PHASE 1 BID RESULTS TERRA ENGRG. & INTEGRITY GRADING & RAWSON MEISE CONSTRUCTION, CONSTR. CORP., EXCAVATING, CONTRACTORS, BID RESULTS MADISON, WIPLAIN, WISCHOFIELD, WIMADISON, WI ITEM APPROX. UNIT OF UNIT TOTAL FOR TOTAL FOR TOTAL FOR UNIT TOTAL FOR ITEMUNIT PRICEUNIT PRICE NO.QTY.MEASUREPRICEITEMITEMITEMPRICEITEM 1.Mobilization/Demobilization1L.S.$ 5,080.00$ 5,080.00$ 10,900.00$ 10,900.00$ 40,565.00$ 40,565.00$ 1,500.00$ 1,500.00 2.Temporary Gas Wells350V.F.$ 60.00$ 21,000.00$ 78.00$ 27,300.00$ 75.73$ 26,505.50$ 265.00$ 92,750.00 3.Bore Hole Abandonment30V.F.$ 20.00$ 600.00$ 25.00$ 750.00$ 45.00$ 1,350.00$ 75.00$ 2,250.00 4.Gas Well Head Assembly, Complete5EACH$ 750.00$ 3,750.00$ 1,920.00$ 9,600.00$ 1,223.79$ 6,118.95$ 1,600.00$ 8,000.00 Install 8" Gas Transfer Pipe With Bentonite 5.670L.F.$ 33.75$ 22,612.50$ 20.00$ 13,400.00$ 23.91$ 16,019.70$ 32.00$ 21,440.00 Wrap Install 10" Gas Transfer Pipe With 6.590L.F.$ 39.00$ 23,010.00$ 23.00$ 13,570.00$ 27.04$ 15,953.60$ 38.00$ 22,420.00 Bentonite Wrap Install 12" Gas Transfer Pipe With 7.195L.F.$ 52.75$ 10,286.25$ 26.00$ 5,070.00$ 41.35$ 8,063.25$ 47.00$ 9,165.00 Bentonite Wrap 8.Install 6" Gas Lateral Pipe990L.F.$ 17.00$ 16,830.00$ 24.00$ 23,760.00$ 18.45$ 18,265.50$ 25.00$ 24,750.00 1 CITY OF JANESVILLE BID DATE: DECEMBER 2, 2009 PUBLIC WORKS BID SCHEDULE "L" - 2009 CONTRACT 2009-29, LANDFILL GAS COLLECTION SYSTEM - PHASE 1 BID RESULTS TERRA ENGRG. & INTEGRITY GRADING & RAWSON MEISE CONSTRUCTION, CONSTR. CORP., EXCAVATING, CONTRACTORS, BID RESULTS MADISON, WIPLAIN, WISCHOFIELD, WIMADISON, WI ITEM APPROX. UNIT OF UNIT TOTAL FOR TOTAL FOR TOTAL FOR UNIT TOTAL FOR ITEMUNIT PRICEUNIT PRICE NO.QTY.MEASUREPRICEITEMITEMITEMPRICEITEM Connection of Gas Transfer Pipe to 9.3EACH$ 1,700.00$ 5,100.00$ 2,300.00$ 6,900.00$ 1,243.18$ 3,729.54$ 755.00$ 2,265.00 Leachate Cleanouts With 6" Pipe Connection of Gas Transfer Pipe to 10.1L.S.$ 1,050.00$ 1,050.00$ 2,700.00$ 2,700.00$ 2,603.41$ 2,603.41$ 1,600.00$ 1,600.00 Existing Horizontal Gas Pipe With 8" Pipe Provide and Install New 6" Valve At 11.1EACH$ 1,750.00$ 1,750.00$ 2,500.00$ 2,500.00$ 2,255.55$ 2,255.55$ 1,350.00$ 1,350.00 Cleanout Connection Install Salvaged 6" Valve At Cleanout 12.2EACH$ 900.00$ 1,800.00$ 2,700.00$ 5,400.00$ 1,219.91$ 2,439.82$ 955.00$ 1,910.00 Connection Provide and Install New 8" Valve On Gas 13.3EACH$ 2,510.00$ 7,530.00$ 2,700.00$ 8,100.00$ 2,509.06$ 7,527.18$ 1,600.00$ 4,800.00 Transfer Pipe Install Salvaged 8" Valve On Connection to 14.1EACH$ 1,000.00$ 1,000.00$ 2,900.00$ 2,900.00$ 2,221.48$ 2,221.48$ 435.00$ 435.00 Existing Horizontal Gas Pipe Supply and Install New 12" Main Line 15.1EACH$ 5,100.00$ 5,100.00$ 5,900.00$ 5,900.00$ 4,719.49$ 4,719.49$ 3,375.00$ 3,375.00 Valve Extend 6" Leachate Cleanout 16.5EACH$ 425.00$ 2,125.00$ 1,400.00$ 7,000.00$ 742.95$ 3,714.75$ 375.00$ 1,875.00 TOTAL AMOUNT - CONTRACT 2009-29: $ 128,623.75$ 145,750.00$ 162,052.72$ 199,885.00 2