Bid Tabs C2009-22, Storm Sewer Improvements CITY OF JANESVILLE BID DATE: 12 AUGUST 2009 PAGE 1 OF 3 PUBLIC WORKS BID SCHEDULE "H" - 2009 CONTRACT 2009-22, STORM SEWER IMPROVEMENTS BID RESULTS R. T. Fox ContractorsIverson ConstructionGlobe ContractorsE & N Hughes Co. BID RESULTS Edgerton, WICottage Grove, WIPewaukee, WIMonroe, WI ITEM APPROX. UNIT OF TOTAL FOR TOTAL FOR TOTAL FOR TOTAL FOR ITEMUNIT PRICEUNIT PRICEUNIT PRICEUNIT PRICE NO.QTY.MEASUREITEMITEMITEMITEM PART A: CENTERWAY & NORTH MAIN STREET WORK: 1.30" RCCP Class III215L.F. $ 100.00 $ 21,500.00 $ 106.00 $ 22,790.00 $ 210.00 $ 45,150.00 $ 175.00 $ 37,625.00 2.72" Dia. Manhole, Complete3EACH $ 2,500.00$ 7,500.00$ 5,450.00$ 16,350.00$ 2,800.00$ 8,400.00$ 3,690.00$ 11,070.00 3.8EACH Type C Inlet Filter, Complete$ 50.00 $ 400.00$ 40.00$ 320.00$ 50.00$ 400.00$ 25.00$ 200.00 4.Trench Dewatering, Complete1L.S. $ 100.00$ 100.00$ 3,500.00$ 3,500.00$ 3,000.00$ 3,000.00$ 1,575.00$ 1,575.00 Storm Sewer/Structure 5.L.S. 1$ 1,000.00$ 1,000.00$ 2,500.00$ 2,500.00$ 2,700.00$ 2,700.00$ 5,278.00$ 5,278.00 Abandonment, Complete Remove and Replace 6.15L.F. $ 40.00 $ 600.00$ 35.00$ 525.00$ 50.00$ 750.00$ 29.50$ 442.50 Concrete Curb and Gutter Remove and Replace 7.75S.F. $ 6.00 $ 450.00$ 7.00$ 525.00$ 7.00$ 525.00$ 6.00$ 450.00 Concrete Sidewalk 8.Concrete Pavement, Type A75S.Y. $ 100.00$ 7,500.00$ 105.00$ 7,875.00$ 60.00$ 4,500.00$ 115.00$ 8,625.00 Asphalt Pavement, Type C, 9.450S.Y. $ 31.00 $ 13,950.00$ 34.00$ 15,300.00$ 24.00$ 10,800.00$ 36.00$ 16,200.00 Complete 10. Granular Backfill, Complete375C.Y. $ 8.00 $ 3,000.00$ 10.00$ 3,750.00$ 12.00$ 4,500.00$ 8.60$ 3,225.00 1 CITY OF JANESVILLE BID DATE: 12 AUGUST 2009 PAGE 2 OF 3 PUBLIC WORKS BID SCHEDULE "H" - 2009 CONTRACT 2009-22, STORM SEWER IMPROVEMENTS BID RESULTS R. T. Fox ContractorsIverson ConstructionGlobe ContractorsE & N Hughes Co. BID RESULTS Edgerton, WICottage Grove, WIPewaukee, WIMonroe, WI ITEM APPROX. UNIT OF TOTAL FOR TOTAL FOR TOTAL FOR TOTAL FOR ITEMUNIT PRICEUNIT PRICEUNIT PRICEUNIT PRICE NO.QTY.MEASUREITEMITEMITEMITEM PART A: CENTERWAY & NORTH MAIN STREET WORK: 11.Excavation Below Subgrade50C.Y. $ 1.00 $ 50.00$ 20.00$ 1,000.00$ 40.00$ 2,000.00$ 20.00$ 1,000.00 12. Traffic Control, Complete 1L.S.$ 1,000.00$ 1,000.00$ 1,000.00$ 1,000.00$ 5,000.00$ 5,000.00$ 2,200.00$ 2,200.00 TOTAL AMOUNT BID - PART A - $ 57,050.00 $ 75,435.00 $ 87,725.00 $ 87,890.50 CENTERWAY & NORTH MAIN STREET: PART B: ST. LAWRENCE AVENUE WORK: 13.12" RCCP Class III325L.F. $ 90.00 $ 29,250.00 $ 48.00 $ 15,600.00 $ 95.00 $ 30,875.00 $ 72.00 $ 23,400.00 14.14" x 23" HE RCCP Class III180L.F. $ 100.00 $ 18,000.00 $ 96.00 $ 17,280.00 $ 118.00 $ 21,240.00 $ 128.00 $ 23,040.00 15.48" Dia. Manhole, Complete3EACH $ 1,500.00$ 4,500.00$ 1,900.00$ 5,700.00$ 1,600.00$ 4,800.00$ 2,530.00$ 7,590.00 16.2' x 3' Type 2 Inlet, Complete3EACH $ 2,000.00$ 6,000.00$ 1,685.00$ 5,055.00$ 1,335.00$ 4,005.00$ 1,167.00$ 3,501.00 17.Type C Inlet Filter, CompleteEACH 6$ 50.00 $ 300.00$ 40.00$ 240.00$ 50.00$ 300.00$ 25.00$ 150.00 18.Trench Dewatering, Complete1L.S. $ 1,000.00$ 1,000.00$ 3,000.00$ 3,000.00$ 3,000.00$ 3,000.00$ 1,575.00$ 1,575.00 2 CITY OF JANESVILLE BID DATE: 12 AUGUST 2009 PAGE 3 OF 3 PUBLIC WORKS BID SCHEDULE "H" - 2009 CONTRACT 2009-22, STORM SEWER IMPROVEMENTS BID RESULTS R. T. Fox ContractorsIverson ConstructionGlobe ContractorsE & N Hughes Co. BID RESULTS Edgerton, WICottage Grove, WIPewaukee, WIMonroe, WI ITEM APPROX. UNIT OF TOTAL FOR TOTAL FOR TOTAL FOR TOTAL FOR ITEMUNIT PRICEUNIT PRICEUNIT PRICEUNIT PRICE NO.QTY.MEASUREITEMITEMITEMITEM Storm Sewer/Structure PART A: CENTERWAY & NORTH MAIN STREET WORK: 19.L.S. 1$ 2,000.00$ 2,000.00$ 2,500.00$ 2,500.00$ 500.00$ 500.00$ 1,607.00$ 1,607.00 Abandonment, Complete Remove and Replace 20.115L.F. Concrete Curb and Gutter, Complete $ 40.00 $ 4,600.00 $ 33.00 $ 3,795.00 $ 20.00 $ 2,300.00 $ 29.00 $ 3,335.00 Asphalt Pavement, Type B, 21.500S.Y. $ 33.00 $ 16,500.00 $ 33.00 $ 16,500.00 $ 26.00 $ 13,000.00 $ 41.00 $ 20,500.00 Complete Asphalt Pavement, Type C, 22.200S.Y. $ 31.00 $ 6,200.00 $ 36.00 $ 7,200.00 $ 28.00 $ 5,600.00 $ 40.00 $ 8,000.00 Complete 23.Granular Backfill, Complete400C.Y. $ 8.00 $ 3,200.00 $ 10.00 $ 4,000.00 $ 12.00 $ 4,800.00 $ 8.60 $ 3,440.00 24.Excavation Below Subgrade50C.Y. $ 1.00 $ 50.00 $ 20.00 $ 1,000.00 $ 40.00 $ 2,000.00 $ 20.00 $ 1,000.00 25.L.S. Traffic Control, Complete 1$ 3,000.00$ 3,000.00$ 1,000.00$ 1,000.00$ 2,000.00$ 2,000.00$ 1,663.00$ 1,663.00 TOTAL AMOUNT BID - PART B - $ 94,600.00 $ 82,870.00 $ 94,420.00 $ 98,801.00 ST. LAWRENCE AVENUE WORK: TOTAL AMOUNT BID - CONTRACT 2009-22: $ 151,650.00$ 158,305.00 $ 182,145.00 $ 186,691.50 3