Bid Tabs C2009-18 New And Replacement Sidewalk
CITY OF JANESVILLE BID DATE: 17 JUNE 2009
PAGE 1 OF 5
PUBLIC WORKS BID SCHEDULE "F" - 2009
CONTRACT 2009-18, NEW AND REPLACEMENT SIDEWALK
BID RESULTS
J.B. Johnson Bros. LLCJW Schultz Const. Inc.Economy Cement Inc.Marvin Gleason Contractor, Inc.
BID RESULTS
Edgerton, WIEdgerton, WIMadison, WIFranksville, WI
APPROX. UNIT OF UNIT TOTAL FOR UNIT TOTAL FOR UNIT TOTAL FOR UNIT
ITEM NO.ITEMTOTAL FOR ITEM
QTY.MEASUREPRICEITEMPRICEITEMPRICEITEMPRICE
1.New Concrete Sidewalk - 4"55,600S.F.$ 2.80$ 155,680.00$ 4.10$ 227,960.00$ 5.60$ 311,360.00$ 5.85$ 325,260.00
New Concrete Sidewalk or
2.2,000S.F.$ 3.10$ 6,200.00 $ 4.60$ 9,200.00 $ 5.70$ 11,400.00$ 6.35$ 12,700.00
Driveway - 6"
New Concrete Sidewalk or
3.400S.F.$ 4.20$ 1,680.00 $ 5.00$ 2,000.00 $ 6.00$ 2,400.00$ 6.85$ 2,740.00
Driveway - 8"
Replacement Sidewalk - 4" (Including
4.3,600S.F.$ 4.35$ 15,660.00$ 6.10$ 21,960.00$ 6.00$ 21,600.00$ 5.85$ 21,060.00
Removal and Restoration)
Replacement Sidewalk or
Driveway - 6" (Including Removal
5.3,400S.F.$ 4.85$ 16,490.00$ 6.60$ 22,440.00$ 6.00$ 20,400.00$ 6.35$ 21,590.00
and Restoration)
Replacement Sidewalk or
Driveway - 8" and greater (Including
6.200S.F.$ 5.70$ 1,140.00 $ 7.00$ 1,400.00 $ 6.00$ 1,200.00$ 6.85$ 1,370.00
Removal and Restoration)
Asphalt and Concrete
Sidewalk/Driveway Removal Only (All
7.500S.F.$ 4.00$ 2,000.00 $ 0.75$ 375.00 $ 0.50$ 250.00$ 1.10$ 550.00
Thicknesses)
1
CITY OF JANESVILLE BID DATE: 17 JUNE 2009
PAGE 2 OF 5
PUBLIC WORKS BID SCHEDULE "F" - 2009
CONTRACT 2009-18, NEW AND REPLACEMENT SIDEWALK
BID RESULTS
J.B. Johnson Bros. LLCJW Schultz Const. Inc.Economy Cement Inc.Marvin Gleason Contractor, Inc.
BID RESULTS
Edgerton, WIEdgerton, WIMadison, WIFranksville, WI
APPROX. UNIT OF UNIT TOTAL FOR UNIT TOTAL FOR UNIT TOTAL FOR UNIT
ITEM NO.ITEMTOTAL FOR ITEM
QTY.MEASUREPRICEITEMPRICEITEMPRICEITEMPRICE
Asphalt Driveway - Removal and
8.50S.Y.$ 4.00$ 200.00 $ 45.00$ 2,250.00 $ 8.00$ 400.00$ 50.00$ 2,500.00
Replacement
2
CITY OF JANESVILLE BID DATE: 17 JUNE 2009
PAGE 3 OF 5
PUBLIC WORKS BID SCHEDULE "F" - 2009
CONTRACT 2009-18, NEW AND REPLACEMENT SIDEWALK
BID RESULTS
J.B. Johnson Bros. LLCJW Schultz Const. Inc.Economy Cement Inc.Marvin Gleason Contractor, Inc.
BID RESULTS
Edgerton, WIEdgerton, WIMadison, WIFranksville, WI
APPROX. UNIT OF UNIT TOTAL FOR UNIT TOTAL FOR UNIT TOTAL FOR UNIT
ITEM NO.ITEMTOTAL FOR ITEM
QTY.MEASUREPRICEITEMPRICEITEMPRICEITEMPRICE
9.Concrete or Asphalt Sawcut1,000L.F.$ 3.00$ 3,000.00 $ 2.50$ 2,500.00 $ 1.00$ 1,000.00$ 2.50$ 2,500.00
Sawcut and Break Off of Curb
(See Detail #29 in Standard
10.1,000L.F.$ 16.00$ 16,000.00$ 15.00$ 15,000.00$ 12.00$ 12,000.00$ 34.00$ 34,000.00
Specifications)
Replacement Curb and Gutter
(Including Removal and
11.3,500L.F.$ 20.00$ 70,000.00$ 31.00$ 108,500.00$ 31.00$ 108,500.00$ 33.00$ 115,500.00
Replacement)
Steel Reinforcing Bars - 1/2"
12.100L.F.$ 0.40$ 40.00 $ 0.75$ 75.00 $ 0.30$ 30.00$ 2.00$ 200.00
(Per L.F. of Bar, Installed)
13.Extra Excavation500C.Y.$ 10.00$ 5,000.00 $ 15.00$ 7,500.00 $ 9.00$ 4,500.00$ 15.00$ 7,500.00
14.Extra Sand or Soil Fill500C.Y.$ 10.00$ 5,000.00 $ 9.00$ 4,500.00 $ 9.00$ 4,500.00$ 20.00$ 10,000.00
15.3/4" Crushed Limestone100TON$ 10.00$ 1,000.00 $ 12.00$ 1,200.00 $ 7.20$ 720.00$ 20.00$ 2,000.00
3
CITY OF JANESVILLE BID DATE: 17 JUNE 2009
PAGE 4 OF 5
PUBLIC WORKS BID SCHEDULE "F" - 2009
CONTRACT 2009-18, NEW AND REPLACEMENT SIDEWALK
BID RESULTS
J.B. Johnson Bros. LLCJW Schultz Const. Inc.Economy Cement Inc.Marvin Gleason Contractor, Inc.
BID RESULTS
Edgerton, WIEdgerton, WIMadison, WIFranksville, WI
APPROX. UNIT OF UNIT TOTAL FOR UNIT TOTAL FOR UNIT TOTAL FOR UNIT
ITEM NO.ITEMTOTAL FOR ITEM
QTY.MEASUREPRICEITEMPRICEITEMPRICEITEMPRICE
16.Standard Concrete Steps50S.F.$ 20.00$ 1,000.00 $ 10.00$ 500.00 $ 15.00$ 750.00$ 50.00$ 2,500.00
4
CITY OF JANESVILLE BID DATE: 17 JUNE 2009
PAGE 5 OF 5
PUBLIC WORKS BID SCHEDULE "F" - 2009
CONTRACT 2009-18, NEW AND REPLACEMENT SIDEWALK
BID RESULTS
J.B. Johnson Bros. LLCJW Schultz Const. Inc.Economy Cement Inc.Marvin Gleason Contractor, Inc.
BID RESULTS
Edgerton, WIEdgerton, WIMadison, WIFranksville, WI
APPROX. UNIT OF UNIT TOTAL FOR UNIT TOTAL FOR UNIT TOTAL FOR UNIT
ITEM NO.ITEMTOTAL FOR ITEM
QTY.MEASUREPRICEITEMPRICEITEMPRICEITEMPRICE
Tree Removal (Including Stump
17.500I.D.$ 35.00$ 17,500.00$ 35.00$ 17,500.00$ 12.00$ 6,000.00$ 75.00$ 37,500.00
Removal and Restoration)
Detectable Warning Field Panel,
18.250EACH$ 220.00$ 55,000.00$ 225.00$ 56,250.00$ 215.00$ 53,750.00$ 350.00$ 87,500.00
2' x 4'
19.Interlocking Block Retaining Wall500S.F.$ 20.00$ 10,000.00$ 33.00$ 16,500.00$ 18.00$ 9,000.00$ 20.00$ 10,000.00
20.Terrace Restoration5,000S.Y.$ 2.00$ 10,000.00$ 3.50$ 17,500.00$ 2.00$ 10,000.00$ 10.00$ 50,000.00
21.Clearing & Grubbing1STATION$ 200.00$ 200.00 $ 300.00$ 300.00 $ 250.00$ 250.00$ 3,000.00$ 3,000.00
Concrete Sealer
22.65,200S.F.$ 0.40$ 26,080.00$ 0.25$ 16,300.00$ 0.30$ 19,560.00$ 1.05$ 68,460.00
TOTAL AMOUNT BID - CONTRACT 2009-18:$ 418,870.00$ 551,710.00$ 599,570.00$ 818,430.00
5