#4 Award of contract 2009-16 (N. Washington/W. Memorial Rehab)DEPARTMENT OF PUBLIC WORKS MEMORANDUM June 1, 2009 TO: City Council FROM: Mike Payne, Engineering Manager SUBJECT: Award of Bid Schedule “E” – 2009 Contract 2009-16, N. Washington/W. Memorial Rehabilitation Summary Bids for Contract 2009-16, N.Washington/W. Memorial Rehabilitation were opened on Wednesday, May 13, 2009. Recommendation Following Review by the Council, the Engineering Division recommends award of Contract 2009-16 to the low bidder and that the City Council express their intent to include in the 2009 Note Issue $125,310.10. Suggested Motion Award the base bid and alternate ‘B’ for Contract 2009-16, N.Washington/W. Memorial Rehabilitation to Frank Brothers Incorporated, and that the City Council express their intent to include in the 2009 Note Issue $125,310.10. Background Contract 2009-16, N.Washington/W. Memorial Rehabilitation This project replaces intermittent curb and gutter and provides for street rehabilitation on N. Washington from Highland Avenue to Hamilton Aveune and on W. Memorial from N. Oakhill Avenue to N. Washington Street. Funding for this project is two sources: 1) $158,300 from the Department of Transportation Local Road Improvement Program, and 2) $125,310.10 from the 2009 Note Issue. We received two (2) bids for this project, with Frank Brothers Incorporated providing the low bid. The Engineering Division is recommending award of this contract to Frank Brothers Incorporated of Janesville, Wisconsin in the amount of $283,610.10. The contract award is the combination of the base bid plus alternate item ‘B’. The alternate bid items for the project are the following: Alternate Bid Item A – Asphalt material grade AC PG 58-28 Alternate Bid Item B – Asphalt material grade AC PG 64-22 Attachment cc: Eric Levitt Jacob J. Winzenz \\petey\cojhome\agenda review\approved agenda items\2009\6-8-2009\contract award bid schedule e-2009 memo.doc Bid Opening: 13 May 2009 Page 1 of 4 CITY OF JANESVILLE TABULATION OF BIDS PUBLIC WORKS BID SCHEDULE “E” – 2009 2009-12 MANHOLE SEALS Maddrell Excavating, LLC Total Bid: $105,908.00 Monroe, WI Odling Construction, Inc. Total Bid: $110,785.00 Delavan WI E & N Hughes Co., Inc. Total Bid: $126,426.00 Monroe, WI Globe Contractors, Inc. Total Bid: $183,240.00 Pewaukee, WI 2009-13 YOUTH SPORTS SITE PAVING AND LIGHTING Rock Road Companies, Inc. Total Bid: $281,278.02 Janesville, WI Frank Bros., Inc. Total Bid: $300,763.83 Janesville, WI 2009-14 WATER AND SEWER SYSTEM IMPROVEMENTS R. T. Fox Contractors, Inc. Total Bid: $69,660.00 Edgerton, WI Odling Construction, Inc. Total Bid: $71,338.00 Delavan, WI Madison Crushing & Excavating Co., Inc. Total Bid: $77,410.32 Madison, WI Globe Contractors, Inc. Total Bid: $92,252.00 Pewaukee, WI \\Petey\COJHome\Agenda Review\Approved Agenda Items\2009\6-8-2009\Contract Award Bid Schedule E-2009 Bid Results.doc Bid Opening: 13 May 2009 Page 2 of 4 CITY OF JANESVILLE TABULATION OF BIDS PUBLIC WORKS BID SCHEDULE “E” – 2009 2009-14 WATER AND SEWER SYSTEM IMPROVEMENTS (Continued) Outside Plumbing, LLP Total Bid: $106,200.00 Janesville, WI Speedway Sand & Gravel, Inc. Total Bid: $108,114.00 Middleton, WI 2009-15 ICE CENTER RENOVATION Corporate Contractors, Inc. Bid No. 1: $166,847.00 Beloit, WI Alternate A-1: $1,936.00 Alternate A-2: $5,409.00 Alternate A-3: $8,681.00 Alternate A-4: $6,071.00 Alternate M-1: $7,482.00 Alternate M-2: $4,439.00 Magill Construction Co., Inc. Bid No. 1: $167,990.00 Elkhorn, WI Alternate A-1: $2,263.00 Alternate A-2: $6,954.00 Alternate A-3: $2,800.00 Alternate A-4: $4,200.00 Alternate M-1: $8,500.00 Alternate M-2: $5,853.00 Maas Bros. Construction Co., Inc. Bid No. 1: $184,400.00 Watertown, WI Alternate A-1: $2,100.00 Alternate A-2: $7,355.00 Alternate A-3: $8,900.00 Alternate A-4: $5,100.00 Alternate M-1: $8,100.00 Alternate M-2: $5,600.00 \\Petey\COJHome\Agenda Review\Approved Agenda Items\2009\6-8-2009\Contract Award Bid Schedule E-2009 Bid Results.doc Bid Opening: 13 May 2009 Page 3 of 4 CITY OF JANESVILLE TABULATION OF BIDS PUBLIC WORKS BID SCHEDULE “E” – 2009 2009-15 ICE CENTER RENOVATION (Continued) Gilbank Construction, Inc. Bid No. 1: $186,300.00 Clinton, WI Alternate A-1: $830.00 Alternate A-2: $9,300.00 Alternate A-3: $3,900.00 Alternate A-4: $4,600.00 Alternate M-1: $8,200.00 Alternate M-2: $5,800.00 Harmony Construction Management, Inc. Bid No. 1: $187,044.00 Madison, WI Alternate A-1: $1,691.00 Alternate A-2: $7,188.00 Alternate A-3: $10,928.00 Alternate A-4: $5,984.00 Alternate M-1: $9,786.00 Alternate M-2: $7,238.00 Paulson Kimball Construction, LLC Bid No. 1: $195,275.00 Janesville, WI Alternate A-1: $1,950.00 Alternate A-2: $8,450.00 Alternate A-3: $1,550.00 Alternate A-4: $4,060.00 Alternate M-1: $7,558.00 Alternate M-2: $5,350.00 Klobucar Construction Co., Inc. Bid No. 1: $198,600.00 Beloit, WI Alternate A-1: $2,200.00 Alternate A-2: $6,800.00 Alternate A-3: $4,800.00 Alternate A-4: $4,780.00 Alternate M-1: $4,900.00 Alternate M-2: $5,070.00 \\Petey\COJHome\Agenda Review\Approved Agenda Items\2009\6-8-2009\Contract Award Bid Schedule E-2009 Bid Results.doc Bid Opening: 13 May 2009 Page 4 of 4 CITY OF JANESVILLE TABULATION OF BIDS PUBLIC WORKS BID SCHEDULE “E” – 2009 2009-16 N. WASHINGTON/W.MEMORIAL REHABILITATION Frank Bros., Inc. Base Bid: $133,342.50 Janesville, WI Alternate A: $162,692.00 Total Base Plus Alternate A: $296,034.50 Base Bid: $133,342.50 Alternate B: $150,267.60 Total Base Plus Alternate B: $283,610.10 Rock Road Cos., Inc. Base Bid: $120,908.10 Janesville, WI Alternate A: $216,720.00 Total Base Plus Alternate A: $337,628.10 Base Bid: $120,908.10 Alternate B: $216,720.00 Total Base Plus Alternate B: $337,628.10 \\Petey\COJHome\Agenda Review\Approved Agenda Items\2009\6-8-2009\Contract Award Bid Schedule E-2009 Bid Results.doc