Loading...
#04 Review of and Council direction on downtown parking structure project Community Development Department Memorandum May 11, 2009 TO: City Council FROM: Brad Cantrell, Community Development Director SUBJECT: Review of Downtown Parking Garage Project SUMMARY The City recently contracted with Arnold & O’Sheridan Inc. to provide engineering, design and cost estimates for the construction of a four level, 225 stall parking garage on the City owned surface parking lot at the corner of North Parker Drive and East Wall Street. The four level parking garage is estimated to cost $4.4 million including engineering design. If authorized to proceed the final design of the structure will be completed for bidding in June and July with construction commencing in September. The parking garage will be completed in the late Spring of 2010. Community Development staff desires to present the parking garage plan to the Council, ask for direction and request authorization to proceed to final design and bidding. STAFF RECOMMENDATION The Community Development Department recommends that following a staff presentation on the parking garage, the City Council authorize staff to proceed to th final design and bidding of the project. On May 4the Plan Commission endorsed the architectural design of the parking garage and forwarded the plan to the City Council with a favorable recommendation. SUGGESTED MOTION Move to authorize staff to proceed to final design and bidding of the Downtown Parking Garage. CITY MANAGER RECOMMENDATION The City Manager recommends approval to proceed with a four level parking garage to accommodate approximately 220 parking spaces. BACKGROUND The Downtown Vision & Strategy completed in 2007 recommends the City focus its efforts at revitalizing existing buildings and increasing activity levels in the core of the downtown. Today’s society requires convenient access and parking for successful business locations. Without adequate parking in close proximity to major activity centers, current development efforts will languish. The Community Development Department believes that the lack of parking readily accessible to the major downtown office buildings has provided a disincentive in attracting office uses in the area. Staff believes that the city should become more proactive in providing parking in the Downtown area. Structured parking is the only viable option available to provide parking that is readily accessible to office buildings in the Downtown area. The City decided to explore a variety of locations and options for a parking structure. Ayres & Associates was contracted in early 2008 to evaluate multiple parking structure designs for locations at Parker Drive & East Wall Street (subject location) and the “Johnson Bank” site along North Main Street. While staff ultimately believes that multiple parking structures will likely need to be constructed in the downtown area, the first priority location was determined to be the Parker/Wall street location. ANALYSIS A. The proposed parking structure will be constructed over the existing surface parking lot at the corner of North Parker Drive and East Wall Street. No property acquisition will be necessary. The structure has been designed to have four levels and provide 225 parking stalls. The structure has also been designed for the future addition of a fifth level if necessary because of increased parking demand. B. Because of the sloping grades existing at this site, access to the ramp will be provided from East Wall Street and North Parker Drive. The “ground level”, or first, level of the parking ramp is designed to be separated from the rest of the structure with access provided only from East Wall Street. The other three levels of the parking ramp will be connected by an internal ramp with access provided from North Parker Drive. By having the other levels separated, the ground level will be more open and allow for more parking stalls and space that could be used for Community Events including the farmer’s market in inclement weather. The fourth floor of the structure will remain uncovered as roof level parking. A four level option has a construction estimate of $4.4 million and would provide 225 parking stalls. Staff has also prepared a preliminary design option for a 3 ½ level structure shown in attached elevations in order to reduce costs. The 3 ½ level structure would accommodate 185 parking stalls and cost approximately $4.1 million. C. Stairwells will be located at the southeast and southwest corners of the structure with an elevator located at the southwest corner. The stairwells and elevator will be accessible to all four floors. D. The structure has been designed to accommodate an enclosed bridge connection from the second level of the ramp to the adjacent Helgesen Building located at 101 East Milwaukee Street. The previous parking structure also had a bridge connection from the ramp to the Helgesen Building. The bridge structure will be bid as an add-on alternate and potentially be constructed with the project if favorable bids are received. Staff has had several discussions with the owner of the building, and feels that this connection is desirable to provide tenants direct access to the structure. The structure has also been designed to allow for a future bridge access to the third floor of the Odd Fellows building located on North Main Street if that is determined necessary in the future. In addition, the structure will provide for pedestrian access from the second level to the alley located on the south side of the structure. E. The existing alleyway located behind 18-22 North Main Street will remain open to allow access to the existing surface parking lot located on North Main Street and provide access to dumpsters located at the rear of the businesses (see attached ground floor site plan). F. The structure will be constructed out of precast concrete as opposed to poured in placed (post-tensioned) concrete which typically has a higher construction cost. The architect has provided two options for the exterior façade: thin brick or molded concrete. The thin brick façade is a technique in which a thin layer of brick is adhered to the precast concrete structure to provide the appearance of a full brick façade. This technique was recently used on the new building constructed by Forward Janesville at 18 South Jackson Street. Molded concrete also provides the appearance of a brick façade by molding and staining concrete to appear as brick. The thin brick option provides more maintenance flexibility by being able to replace chipped or damaged pieces of the façade, and there is no need to repaint or stain the surface over time. However, a thin brick façade typically has a higher upfront cost. Overall budget considerations will predicate which façade surface is ultimately used. G. Because the building is within the Downtown area and adjoining the East Milwaukee Street and North Main Street National Register Historic districts the parking garage design committee was concerned that the structure be designed in a manner sensitive to the surrounding buildings. The architect looked at several buildings in the Downtown area in order to incorporate details similar to those buildings including cornice treatments, window and building rhythms, etc. Those buildings included the former PC Computer building at 101 W. Milwaukee Street, the Carriage House at 10 N. Parker Drive, the Riverfront Center on West Milwaukee Street and the Old Town Mall on South Main Street. (See attached photo’s of buildings). The structure is designed with an internal ramp which will allow the top three floors of the parking ramp to be level and provide a more horizontal and uniformed appearance from the street (see attached building elevations). This will allow the structure to appear more as a building than a parking garage and help blend in with the surrounding buildings in the area. H. The proposed parking structure is planned to be constructed over the existing surface parking lot located at the southwest corner of East Wall Street and North Parker Drive. The existing surface parking lot contains 84 spaces. The parking structure has been designed to have 50 parking stalls on the ground level and approximately 12 of the existing surface spaces will remain outside of the structure (see attached site plan). I. As typically occurs with larger facility construction projects, a parking garage committee was created to assist in the design and review of the facility. Committee representatives include several members of City staff, various downtown stakeholders, and Councilmember Brunner. This committee has worked with the consultant on the overall design and functionality of the garage, as well as the architecture and aesthetics. The committee has reviewed and approved the proposed design of the structure. J. This lot was previously developed as a multi-level parking structure, originally constructed in 1958 which accommodated a total of 179 parking spaces. The parking structure was demolished in 2001 and converted into the existing 84 space surface lot. Currently, the surface lot contains 41 two-hour, 39 leased and four handicapped spaces. A portion of the stalls in the new structure may be designated for leased parking to the individuals in the area. SARA Investments, the owners of 101 East Milwaukee Street, have requested that some leased parking be assigned to its building. Determination of the number of leased spaces will be considered by the City Council in the review of a TIF development agreement. If leased spaces are created they would be leased from 6:00 a.m. to 6:00 p.m. Monday through Saturday and available to the general public following lease hours. K. In 1998 the City hired Walker Parking Consultants to determine how much parking was needed in the Downtown at that time and for the next 10 years. The study included an analysis of the removal of the former parking garage at Wall and Parker Drive and the Parking Plaza. The study considered the overall parking demand and supply for the Downtown but also analyzed it on the basis of activity centers. One of the activity centers includes the two blocks bounded by Wall Street/Parker Drive/East Milwaukee Street and the Rock River. Staff updated the study based on change of land uses within these blocks including the addition of two bars; Wiggy’s and Quotes. Staff has determined that the total parking demand in this area is 296 spaces at full building occupancy. The parking supply in the two blocks not including the existing Wall Street/Parker Drive lot but counting the on street parking adjoining the blocks and the public and private lots is 76 spaces. This creates a net parking demand of 220 spaces (296-76 = 220). The new structure is designed for 225 new spaces, not including the 12 surface stalls that will remain (total 237). L. City staff held a public open house on April 22 to review the preliminary design and architecture of the proposed parking garage. Staff sent out notices to property owners within a two block area and members of the Downtown Development Alliance (DDA). Approximately 25 individuals attended this meeting in addition to City Staff members and the engineering consultants. Members of the public asked general questions on the scheduling of the proposed parking garage. Staff indicated that following Plan Commission review and City Council endorsement, staff would proceed on the detailed engineering design, award BIDs in August and construction could commence in September of this year. The project would likely then be completed in the late Spring of 2010. Individuals asked what the City would be doing to accommodate parking in the interim when this parking lot is taken out of service. Staff will work with business and property owners to direct customers to other nearby public lots including the Parking Plaza, South Main Street and East Wall Street lots. A copy of the informational handout distributed at the public open house is attached for your review. th M. The Janesville Historic Commission reviewed the project at its April 27 meeting. The Commission voted unanimously to endorse the proposed parking garage design concept as submitted but further expressed a desire to review the final colors to be selected at a later date. The Commission also suggested that a medallion symbol be used as an ornamental feature on the wall panel between the columns at the top level of the garage instead of the offset masonry square as shown in the rendering. N. The four level parking garage containing 225 and is estimated to cost $4.4 million including the cost of engineering and contingency. Staff desires to bid the project in two phases. The first phase is the pre-cast structure and according to engineers would account for approximately 50% of the cost of the project. This portion would be bid in June. The remainder of the project would be bid in late July. By biding the project in two phases the city should have a good understanding of the estimated cost early in the process. In order to reduce the cost of the project, the Design Committee recommended that a 3 ½ story parking structure be also be bid as a possible alternative. Although the Committee believed that a four level structure was preferable to better address long term parking demands in the area, they believed that it should be a potential option for consideration. The project engineers estimated that this would reduce the overall cost to $4.1 million, but will also reduce the number of parking spaces to 185. In addition to project reductions, the Design Committee also recommended that a number of items be bid separately and considered for inclusion in the project if favorable bids were received. Those items include: the use of thin brick on the exterior ($108,000); the pedestrian bridge to 101 E. Milwaukee Street ($103,000); a canopy over the forth level access ramp ($41,000); and concrete on the ground level instead of asphalt ($26,000). The Design Committee believed that these items would add value and durability to the project such as use of thin brick instead of stained molded concrete; use of concrete on the ground floor instead of asphalt; and inclusion of the canopy over the forth level access ramp when snow and ice conditions occur. Although desirable these items were not considered essential if costs needed to be reduced. Additionally, the Committee believed that the pedestrian connection to 101 E. Milwaukee would provide convenience for the patrons of that building however that amenity could also be added in the future. O. In 2008, $1.25 million was placed in the note issue for construction of the parking garage. The Administration proposes to place another $1.0 million in the note issue for this year with the balance of funding to be borrowed in the following year 2010. The Administration has used this multi-year funding approach on other large projects including police station, the proposed central fire station, etc. in order to avoid a large amount of general fund debt borrowing in any one year. Typically a project of this scale takes approximately one year to engineer and bid and another year for construction. PLAN COMMISSION ACTION – MAY 4, 2009 Brad Cantrell, Community Development Director, provided the Plan Commission with an overview of the proposed downtown parking garage structure. Cantrell provided information regarding the architectural design, operational facilities, parking stall capacity, proposed elevations and estimated cost alternatives. Questions and discussion from Plan Commission Members: Commissioner Werner asked what the Plan Commission’s architectural review of this item includes. Cantrell indicated that Plan Commission can consider various aspects of the structural design and appearance but should not evaluate the estimated cost factors. Commissioner Werner asked about the Historic Commission’s role in review of the structure. Cantrell indicated the Historic Commission reviewed the design and endorsed the architecture but does not have final authority. Cantrell suggested the Plan Commission comment on those aspects of the facility they feel should be included in the design. Commissioner Voskuil asked how many parking stalls were included in the 3 ½ versus 4-story design alternatives. Cantrell indicated 185 stalls are included in the 3 ½-level design while 225 stalls would be in the four-level plan. Commissioner Voskuil asked Cantrell to describe the add-on items which were not included in the estimated 4.4 million-dollar facility. Cantrell indicated the proposed add-on costs would be approximately $250,000 in total for the canopy over the ramp, application of thin brick exterior treatments and construction of a pedestrian walkway connected to the SARA Investment building. Commissioner Werner asked about the life expectancy for the structure and if estimated maintenance costs were available for the different façade treatments. Cantrell indicated the parking garage has a 40-50 year life span and maintenance costs for the exterior were unavailable at this time however the painted molded brick would need to be repainted. Commissioner Zolidis asked if any other ground-level events were planned for this portion of the structure during inclement weather. Cantrell indicated that in addition to the Farmer’s Market, the building design allows for various types of temporary use options that may not be known at this time. Commissioner Zolidis asked if any energy efficiency lighting was proposed within the structure and asked Cantrell for background information on parking demand figures in the area. Cantrell indicated that LED and induction lighting is being considered for the facility. He stated that the update to the Walker Parking Study indicated a need for approximately 220 parking stalls within this immediate development cluster area of the downtown in addition to the existing 75 parking stalls in the area. Commission Hanewold asked if a certain number of stalls would be designated for use by Sara Investments. Cantrell indicated that Sara Investments would like to lease a certain amount of parking stalls within the structure but the number is not yet determined. Chairman Helgerson asked about the existing parking lots located east of the proposed structure and questioned if pedestrian accessibility was considered at the corner of North Parker and Wall Street. Cantrell indicated that the parking lots to the east were public parking lots containing approximately 115 stalls in total; however, the location of these spaces was outside the activity area that defines the need for additional parking along Main Street. Cantrell indicated that there was considerable discussion by the steering committee regarding the location of stairwells at the corner of N. Parker and Wall Streets, but the largest demand for pedestrian accessibility is directed toward Main and Milwaukee Streets. Commissioner Perrotto asked if the recommendation to move forward with the parking garage is based on the need for additional parking regardless of Sara Investments proposal. Cantrell stated an economic opportunity will come with the construction of the parking garage. The structure is needed to ignite and accelerate growth and redevelopment in the downtown area. There was no further discussion regarding this item. There was a motion by Commissioner Werner to endorse the architectural design of the downtown parking garage and forward the plan to the City Council with a favorable recommendation noting that the Plan Commission has not reviewed the financial aspects of the proposal. The Commission’s endorsement included the use of thin brick because of potential long-term maintenance savings, the substitution of the metal vertical columns in place of the precast elements due to cost savings, that a four-level structure be constructed and that the brick color be cream city brick. The motion was seconded by Commissioner Voskuil and was unanimously approved. cc: Jacob J. Winzenz, Dir. of Administrative Services/Assistant City Manager