#06 Award of Contracts DEPARTMENT OF PUBLIC WORKS MEMORANDUM April 2, 2009 TO: City Council FROM: Mike Payne, Engineering Manager SUBJECT: Award of Bid Schedule “C” – 2009 Contract 2009-7, Washington/Memorial Street Reconstruction Contract 2009-8, Manhole Reconstruction Contract 2009-9, Landfill Scale Replacement Summary Bids for Public Works Bid Schedule “C” – 2009, Contracts 2009-7, -8, -9 were opened on Wednesday, March 25, 2009. The Engineering Division is recommending the Council reject the only bid received for contract 2009-7, Washington/Memorial Street Reconstruction because it exceeds the project budget. The Engineering Division is recommending award of contracts 2009-8, Manhole Construction and 2009-9, Landfill Scale Replacement to the low bidders, as shown on the attached tabulation of bids and that the City Council express their intent to include in the 2009 Note Issue $28,860 for manhole replacement and $90,000 for the landfill scale replacement. Recommendation Following Review by the Council, the Engineering Division recommends rejecting the only bid received for contract 2009-7 and awarding contracts 2009-8 and 2009-9 to the low bidders and that the City Council express their intent to include in the 2009 Note Issue $28,860 for manhole replacement and $90,000 for the landfill scale replacement. Suggested Motion Move to award contracts 2009-8 and 2009-9, to the low bidders and express our intent to include in the 2009 Note Issue $28,860 for manhole replacement and $90,000 for the landfill scale replacement. City Manager Recommendation I concur with staff’s recommendation. Background Contract 2009-7, Washington/Memorial Street Reconstruction This project includes curb and gutter replacement and street resurfacing on Washington Street from Highland Avenue to Hamilton Avenue and on W. \\petey\cojhome\agenda review\approved agenda items\2009\4-13-2009\contractawardbidschedulecmemo2009.doc Memorial Drive from Oakhill Avenue to the west bridge abutment at the Rock River. The total length of this project is 1.1 miles. Although there were five (5) prequalified plan holders, Rock Road Companies, Inc. submitted the only bid for this project in the amount of $464,288.64. Funding for this project included $158,000 of Local Road Improvement Program (LRIP) monies and $233,000 of 2009 Note Issue borrowed funds for an anticipated project cost of $391,000. The averaged unit price of asphalt on this contract is th 28% higher than the street resurfacing contract bid January 28 of this year. The City of Janesville has never experienced asphalt prices this high and the project is over budget. The Engineering Division recommends rejecting this bid and intends to modify the project scope for rebid in May. Contract 2009-8, Manhole Reconstruction This project replaces existing sanitary sewer, water valve, and storm sewer manholes in paved streets prior to the 2009 annual resurfacing contract. This is the second year of an annual program for maintaining utility manholes in conjunction with the street maintenance program. Funding for this project is from various sources: the sanitary manholes are funded with $127,310 Wastewater Utility operating funds; the storm sewer manholes are funded with $23,185 stormwater utility funds; and the water valve manholes will be funded by $28,860 of 2009 Note Issue borrowing. We opened four (4) bids for this project with Infrastructure Techologies providing the low bid. The Engineering Division is recommending award of this contract to Infrastructure Technologies of Rogers, Minnesota, in the amount of $179,355. Contract 2009-9, Landfill Scale Replacement This project replaces the existing scale at the landfill which is 25 years old and has reached the end of its useful life. Funding for this project will be borrowed in the 2009 Note Issue ($90,000) which covers the scale replacement contract and miscellaneous materials furnished by the City. We opened four (4) bids for this project with United Scale and Engineering providing the low bid. The Engineering Division is recommending award of the contract to United Scale and Engineering of Madison, Wisconsin, in the amount of $76,602. This includes the base bid and the alternate bid to upgrade from a 10-foot wide to an 11-foot wide scale system. Attachment cc: Eric Levitt Jacob J. Winzenz \\petey\cojhome\agenda review\approved agenda items\2009\4-13-2009\contractawardbidschedulecmemo2009.doc Bid Opening: 25 March 2009 CITY OF JANESVILLE TABULATION OF BIDS PUBLIC WORKS BID SCHEDULE “C” – 2009 2009-7 N. WASHINGTON/W. MEMORIAL STREET REHABILITATION Rock Road Companies Total Bid: $464,288.64 Janesville, WI 53547 2009-8 MANHOLE RECONSTRUCTION Infrastructure Technologies Total Bid: $179,355.00 Rogers, MN E & N Hughes Company Total Bid: $222,942.00 Monroe, WI R. T. Fox Contractors Total Bid: $293,140.00 Edgerton, WI Globe Contractors Total Bid: $460,391.00 Pewaukee, WI 2009-9 LANDFILL SCALE REPLACEMENT United Scale & Engineering Total Bid: $76,602.00 Madison, WI Gilbank Construction Total Bid: $80,075.00 Clinton, WI Fairbanks Scales Total Bid: $98,487.99 Milwaukee, WI Klobucar Construction Total Bid: $103,785.00 Beloit, WI \\Petey\COJHome\Agenda Review\Approved Agenda Items\2009\4-13-2009\Bid Results Bid Schedule C-2009.doc