Advertisement For Bids Public Works Bid Schedule C-2009
23 February 2009
PART #1
CITY OF JANESVILLE
ADVERTISEMENT FOR BIDS
PUBLIC WORKS BID SCHEDULE “C” – 2009
The City of Janesville, Wisconsin hereby gives notice that it will receive sealed bids for the
following listed Public Work:
C2009-7 N. Washington/W. Memorial Drive Street Rehabilitation
– For
furnishing all the labor, materials, equipment, and doing all the
work necessary for the construction and completion of 30,000
S.Y. asphalt pavement milling; 400 L.F. loop detector conduit;
300 L.F. traffic signal conduit; 1,200 L.F. loop detector wire;
3,000 S.Y. concrete pavement removal; 2,000 L.F. curb and
gutter replacement; 4,000 S.F. concrete flatwork; 3,000 ton
crushed stone base; 4,500 ton asphalt paving; 12,000 L.F. epoxy
pavement markings; and traffic control. This is a Local Road
Improvement Program project.
C2009-8 Manhole Reconstruction
– For furnishing all the labor,
materials, equipment, and doing all the work necessary for the
structural rehabilitation and associated street restoration of
approximately 140 existing sanitary sewer, water valve, and
storm sewer manholes on existing paved streets.
C2009-9 Landfill Scale Replacement
– For furnishing all the labor,
materials, equipment, and doing all the work necessary to supply
and install a new 100-ton scale at the City Landfill including
removal of existing pit scale system.
2:00 P.M. LOCAL TIME ON WEDNESDAY, THE 25TH
Sealed bids will be received until
DAY OF MARCH, 2009.
All bids shall be addressed to the City Clerk’s Office, City of
Janesville Municipal Building, 18 North Jackson Street, Janesville, Wisconsin, 53548, and
shall be enclosed in a SEALED ENVELOPE, marked with the name and address of the
Bidder and Contract Title for which the bid is being submitted. All bidders shall bid in
accordance with, and shall bid upon, the bid forms included in the Contract Documents.
Bids will be opened in the Council Chambers at 2:01 P.M. on the same date. The above
Public Work will be let to the lowest responsible bidder and must be performed in
accordance with the plans, specifications, and contracts on file with the City Clerk.
PART #1
CITY OF JANESVILLE ADVERTISEMENT FOR BIDS PAGE 2
.
PUBLIC WORKS BID SCHEDULE “C” – 2009 23 FEBRUARY 2009
No bid will be read or considered unless accompanied by a certified check equal to 10
percent of the bid or a bid bond in equal amount, payable to the City as guaranty that if the
bid is accepted, the bidder will execute and file the proper contract and bond within ten
days from the date the lowest responsible bidder's bid is accepted. In case the bidder fails
to execute such contract and bond within the time set by the City, the check or bid bond
shall be forfeited to the City as liquidated damages.
The form of contract and bond and questionnaire to show bidder's proof of responsibility in
accordance with Section 66.29(2) Wisconsin Statutes, as well as the plans and
specifications, are on file and may be obtained at the City Engineer's Office, Municipal
Building.
WEDNESDAY, MARCH
Plans and detailed specifications are scheduled to be available on
4, 2009non-refundable
. A $30.00 deposit is required for each set of Contract
Persons requesting plans by mail shall include an additional
Documents.
non-refundable $10.00 mailing fee for each set.
In addition, bidders are required to
have a copy of the Standard Specifications for Public Works Construction, which may be
purchased at the City Engineering Office for $30.00 per copy.
The wage scales to be paid on these projects are enclosed in the Contract Documents, as
well as on file in the City Clerk’s Office, and all work is subject to Section 66.293 of
Wisconsin’s Statutes.
PROOF OF RESPONSIBILITY
forms for this project must be filed in the Engineering
12:00 NOON, WEDNESDAY, MARCH 11, 2009
Division Office not later than . Forms are
located in the Contract Documents and available at www.ci.janesville.wi.us (Documents &
Maps; Document Library; Engineering Department; Bidder’s Proof of Responsibility).
Forms shall show sufficient financial ability, equipment, and experience to perform the
Contract. The decision regarding qualifications shall be final.
Said work shall be commenced by, and shall be entirely completed by, the dates set in the
proposal for the specific work.
The determination of the lowest and best bid will be decided by the City Engineer, subject
to review by the City Council. The Council reserves the right to reject any and all bids.
No bidder may withdraw his bid within 45 days after the actual date of the bid opening.
2 MARCH & 9 MARCH
Published in The Janesville Gazette and the Western Builder on
2009.