Addendum Landfill Phase 3 Construction C2009-2
City of Janesville
P.O. Box 5005 Janesville, WI 53547-5005 608-755-3160
??
27 January 2009
PUBLIC WORKS BID SCHEDULE “A” – 2009
CONTRACT 2009-2, LANDFILL PHASE 3 CONSTRUCTION
ADDENDUM NO. 1
The following changes/modifications shall be made to the Detail Specifications and Bid Proposal
for this contract:
1.) Delete Bid Item No. 42 from the Bid Proposal. A revised Bid Proposal is not attached. The
Contractor shall draw a line through that bid item and not include a unit or total price for that
item.
2.) In relation to the deletion of the bid item, the Contractor shall note a modification in Section
11.9.3, Grading, of the Detail Specifications. The fourth line of that paragraph notes an
estimated quantity of 875 C.Y. The correct quantity is 785 C.Y. and is consistent with Bid
Item No. 5.
3.) This item clarifies the first paragraph in Section 11.5.2, Pump Controls. That paragraph is,
“Contractor shall supply and install pressure systems, KPSI Series 700 transducer stainless
steel construction with Aneroid Bellows and surge protection, or equal”. This paragraph
shall be moved to Section 11.5.1, Leachate Pump. The last paragraph of Section 11.5.1,
which describes payment, shall include payment for the transducer and sensor wire to the
disconnect panel and shall be part of Bid Item No. 21, Leachate Pump System, Complete.
4.) Add to end of paragraph 2 of Section 11.2.4, Preparation of Subbase – Phase 3, the
following: The Birdseye/sand mixture will be in stockpile west of Phase 3 prior to start of
this work. The materials will be in two separate stockpiles, 2/3 Birdseye and 1/3 sand. The
Contractor shall uniformly mix the material as it is placed in the one-foot lift.
ACKNOWLEDGE RECEIPT BY RETURN FAX TO 608/755-3189:
YES, I AM IN RECEIPT OF ADDENDUM NO. 1 TO
CONTRACT 2009-2, LANDFILL PHASE 3 CONSTRUCTION:
_____________________________________________
Signature
_____________________________________________
Plan Holder
_____________________________________________
Date